Landfill Hearing: Day 1 recording and recap; what to expect on Day 2

Day 1 recap

The Public Hearing on LU-24-027, Republic Services’ application for the proposed expansion of the Coffin Butte Landfill, began on Tuesday, April 29. Benton County Planning Commission Chair Nicholas Fowler started the meeting at 6 p.m. The County’s Planning Division presented the staff report. Planning Commission members asked many follow-up questions that were addressed by the County’s Planning Official, consultants and representatives from Republic Services. The Hearing was recessed around 8:45 p.m.

View the recording of Day 1.

Day 2 expectations

Presentation and discussion of the staff report on Day 1 took more time than projected. Republic Services’ presentation, planned for the first meeting, will take place when the hearing resumes at 6 p.m. on Thursday, May 1. The Planning Commission will then move on to public verbal testimony if time permits.

If the applicant presentation and subsequent discussion fills the scheduled meeting time, public testimony will likely begin on Tuesday, May 6.

The hearing is open to the public in the Holmes & Shipley Meeting Room on the first floor of the County’s Kalapuya Building at 4500 SW Research Way in Corvallis, OR. The room has a posted capacity of 133 people, although fewer can be accommodated during the staff and applicant presentation portion of the hearing while tables are in place for the presenters. A viewing/listening room is available on the second floor of the Kalapuya building. An additional overflow space, not utilized on Day 1, will be opened on the first floor.

Attendees who need any physical or language accommodations should notify Benton County Community Development (permitcheck@bentoncountyor.gov) at least 72 hours in advance of the hearing.

The hearing can also be viewed through Zoom.

Verbal and written testimony

A new batch of compiled written testimony was posted to Munidocs on April 29. This includes comments received through noon on April 28.

Written testimony is still being accepted in four ways: online form, regular mail, email (publiccomment@bentoncountyor.gov) and hand delivery. Details are available on the Coffin Butte Landfill webpage.

Members of the public can sign up to share verbal testimony during the hearing. Names will be added to the verbal testimony roster in the order in which they are submitted, either through the webform or in person at the public hearings. A testimony sign-up table is available in the lobby beginning one hour prior to meeting start times. Verbal testimony is limited to three (3) minutes per person.

Registration for verbal testimony will be open as long as the Public Hearing is in session or until 6 p.m. on May 6, whichever comes first.

Four ways to submit written comments about the proposed landfill expansion application

Members of the public are invited to submit written testimony about Republic Services’ Conditional Use Permit application (LU-24-027). Planning Commissioners will receive the full text of all written comment submitted. It will not be edited or summarized.

There are four ways to submit written testimony:

Submit testimony online

Regular Mail (USPS)
Benton County Community Development
4500 SW Research Way
Corvallis, OR 97333-1139

Email
publiccomment@bentoncountyor.gov

Hand Delivery
Community Development is located on the second floor of the Kalapuya Building at 4500 SW Research Way in Corvallis, OR. The office is open Monday – Friday from 8 a.m. to 5 p.m.

Timeline for Written Testimony

The deadline to submit written testimony will be determined by the length of the Public Hearing. As long as it is open, written public comments will be accepted into the record. Once all verbal testimony is received, the Planning Commission chair will determine when the Public Hearing should be closed. The schedule provided above is planned and expected, but those dates are not guaranteed as less time might be required for verbal testimony.

After the public hearing, all written comments that were not in the original staff report will be added to the record and posted to the County website in one action. 

Expected Hearing Schedule

Tuesday, April 29, 6 – 9 p.m.              Day 1: Staff report, applicant presentation and start public testimony if time permits
Thursday, May 1, 6 – 9 p.m.Day 2: Start or continue public testimony
Tuesday, May 6, 6 – 9 p.m.Day 3: Continue public testimony as necessary
Tuesday, June 17, 6 p.m. – completeDay 4: Deliberations and decision

Find more information about the landfill and the application for proposed expansion on the Coffin Butte Landfill page.

Hearing dates set for landfill expansion application, public comment period now open

The Benton County Planning Division has announced the schedule for the public hearing on Republic Services’ Conditional Use Permit application for the proposed expansion of the Coffin Butte landfill.

The public comment period is now open. The following dates have been set for the hearing before the Benton County Planning Commission.

Tuesday, April 29, 6 – 9 p.m.              Day 1: Staff report, applicant presentation and start public testimony if time permits
Thursday, May 1, 6 – 9 p.m.Day 2: Start or continue public testimony
Tuesday, May 6, 6 – 9 p.m.Day 3: Continue public testimony as necessary
Tuesday, June 17, 6 p.m. – completeDay 4: Deliberations and decision

The hearing will be held at the County’s Kalapuya Building at 4500 SW Research Way in Corvallis. Anyone can sign up as an Interested Party to receive updates about the status of the CUP application and changes or additions to the schedule.

County invites comment from public

Members of the public can now submit written testimony about the CUP application.

After the public hearing, all written comments that were not in the original staff report will be added to the record and posted to the County website in one action. 

Members of the public can also sign up to share verbal testimony during the hearing. An online sign-up system will be released about a week before the hearing begins. Although this option will be available, the community is encouraged to provide written comments in advance so Planning Commission members, County staff and the public have time to consider all perspectives and prepare to respond at the hearing. This also allows for the most efficient use of meeting time.

Addendum submitted, now available to public

Republic Services submitted additional material for the CUP application on March 14, 2025. This addendum to the Burden of Proof (submitted on Jan. 15) is publicly available on the Munidocs platform as Landfill Expansion Application, 1st Addendum to Burden of Proof.

The Benton County Planning Division is working to incorporate this new information into the staff report.

View Republic Services’ CUP application online:

To learn more about the decision process, visit bentoncountyor.gov/coffin-butte-landfill.

Back to top